Ice rink slab
Work is underway on the ice rink slab. (Photo: Kirkner)
Town Senior Associate Civil Engineer Peter Bernasconi confirmed that work has begun on the ice rink slab.
“It should be completed by mid-October, which means we will be able to make ice for the Dec. 2 Grand Opening,” Bernasconi said.
Currently the contractor is moving some lighting and digging holes for pipeline. The actual slab is expected to be poured at the end of September.