MUF Appears Stuffed

  • by Jack Lunch
  • in News
  • — 27 Apr, 2018

Low bid comes in at $18.8 million 

Once the second number was read, they scattered, leaving the Town’s Assistant Engineer, a visibly annoyed Haislip Hayes, to answer a few scattered questions from representatives of the two bidding firms and one journalist.

“They” being the eight or so curious Town staffers, who had assembled in the hopes of witnessing a miracle that did not occur.

At the Wednesday, April 18 Mammoth Town Council meeting, Public Works Director Grady Dutton had said at one point, in an aside, that he was optimistic the proposed Multi-Use Facility project might draw up to five bidders.

At the actual bid opening on April 25, there were only two bidders: Spiess Construction of Santa Maria and AMG Construction of Santa Clarita.

Spiess’s base bid: $19.8 million.

AMG’s base bid: $18.8 million.

Click here for more.

Share

Topics: Haislip HayesMUFSpiess Construction

— Jack Lunch

Jack is the publisher and editor of The Sheet. He writes a lot of page two's.

You may also like...

  • LIFE IN MAMMOTH: IT’S IN TENTS 7 Jun, 2019
  • Hollywood MUF 23 Dec, 2016
  • What’s Next? 4 May, 2018
  • SKINNIER MUF 4 Aug, 2018
  • Previous story Remote Control
  • Next story Cooking the (Face)books
  • Special Publications

  • Recent Posts

    • GET A PIECE OF THE ROCK
    • OBITUARY: BRIAN SIEBERT 1973-2026
    • SEAL OF APPROVAL
    • GIVE ME LIBERTY OR GIVE ME … $1.1M
    • IT’S A HARD KNOCK LIFE FOR BEARS
  • Special Publications

  • News
    • Mountain Town News
    • Sports and Outdoors
  • Arts and Life
  • Opinion/Editorial
  • Letters to the Editor
  • Dining

© 2026 THE SHEET. DEVELOPED BY PENDERWORTH.